Mountain Vista Estate

Stages 1 & 2

  • Stages 1 & 2 are on schedule for completion by early December 2023, with the title expected shortly thereafter. Settlement is anticipated in December 2023 / January 2024, and regular updates will be provided.
  • Block 1 has successfully completed all construction phases, including final inspections and council approval.

 

  • Blocks 2, 4, and 6 are progressing as planned, with settlements anticipated in January / February 2024.
    The road connecting stages 2 & 3 has been finished, enhancing accessibility and connectivity within the project.
Rectangle 3475

Stage 3

  • Stage 3 is actively under construction, with substantial progress noted.
  • Concrete pouring is underway for the ground floor of the apartment and commercial block, while the first-floor framing is already in place.

 

  • Blocks 16 & 18 framing has been completed, and we anticipate the framing for 15 & 17 before Christmas.
  • Site offices and storage containers along the road front are being relocated or removed to facilitate the preparation of concrete pads for blocks 19 - 22.
Rectangle 3475

Explore Mountain Vista Estate

Mountain Vista Estate

In this project update, we are excited to share the significant milestones achieved in recent months and to offer a glimpse into the promising future that lies ahead. Our commitment to excellence, the dedication of our team, and your support have all played crucial roles in bringing this vision to life.

Please read on to discover the remarkable progress and the path we’re embarking on as we continue our journey towards creating a truly exceptional living experience at Mountain Vista Estate.

Block 1

• Interior painting is complete.
• Timber flooring is complete.
• Waterproofing and tiles are 95% complete.
• Finishing lines are complete in Units 1 & 2, and      90% complete in Units 3, 4 & 5.
• Second fix plumbing is 30% complete.
• Second fix electrical and mechanical is 50% complete.

Block 2

• Membrane gutters are currently at 50% completion.
• RAB / Play installation is currently at 60% completion.
• Exterior building wrap is at 95% completion.

Rectangle 3475

Block 3

• Interior door installation is complete.
• Finishing lines are currently substantially complete across all units.
• Plaster is substantially complete across all units.
• Waterproofing and tiles are substantially complete.

 

Block 4
• Roof installation has been completed.
• Windows are currently not on site for installation.
• RAB / Ply installation is at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 5

• Finishing lines are 80% complete across each unit.
• Paint is substantially complete.
• Waterproofing and tiles are substantially complete across all units.
• Kitchen joinery is being installed within 5 of the 8 units. Currently 80% complete across these units.
• 2nd plumbing fix is 30% complete across all units.

Block 6

• Roof installation has been completed.
• Window installation is at 75% completion and progressing.
• RAB / Ply is currently at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 7

• Roofing and flashings complete.
• Waterproofing and tiles are substantially complete across all units.
• Paint sealer coat has been completed across all units.
• Paint topcoat is currently 70% complete across all units.

 

Block 8

• First fix has been completed across all units.
• Insulation and Intello have been completed across all units.
• Battens have been installed across all units.
• Gib work has commenced on 2nd October.

Rectangle 3475

Block 9

• Gib installation has been completed.
• Finishing lines are 70% complete across all units.
• Plastering is progressing at 50% throughout the remaining units.
• Internal doors are currently being installed.

 

Block 10

• 1st fix has been completed across all units.
• Gib installation on walls has been completed across all units.
• Ceiling gib is currently progressing.

 

Block 11

• 1st fix has been completed across all units.
• Insulation and Intello has been completed across all units.
• Battens have been installed across all units.
• Gib installation is currently progressing across all units.

Block 12

• Stairs have been installed across all units.
• 1st fix has been completed across all units.
• Insulation and Intello has been installed across all units.
• Structures are all complete.
• All roof installation and finishes have been completed.
• All windows have been installed.
• Battens have been installed across all units.
• Gib installation on walls is currently progressing.

 

Block 13

• Basement beams have been installed.
• Basements slabs have been installed.
• Installation of Novacoil & Scoria is currently 75% complete with backfill.

Explore Mountain Vista Estate

Verge Apartments

It brings us great pleasure to provide you with the latest updates on our Verge Apartments project. Our team has been diligently working to bring this vision to life, and we are excited to share the significant progress we’ve made.

From the successful installation of the plumbing system to the ongoing pre-wiring and advanced weather line installations, we have reached important milestones. The internal studs are now in place, and the roofing is fully installed.

Rectangle 3475

East Building

• Construction of block wall in the West Building elevation has been completed.
• Roof diamondtek sheeting installation has been completed.
• Internal steel framing on level 2 of the East Building has been completed.
• Penetrations through ComFlor in the East Building have been completed.

• Installation of additional steelwork to the lift shaft has been completed.
• The installation of RAB weather-line and proclima paper is now ongoing with installation progressing from the top-down.
• The completion of external intumescent paint to all floors is ongoing.
• The pouring of topping slabs to falls for all balconies is nearing completion.

Rectangle 3475
Image 2

West Building

• Installation of internal steel framing is ongoing with the demark of all apartments underway.
• Ongoing installation of Airmaster mechanical equipment on Level 4.
• The installation of the roof structure on Level 4 has been completed.
• The pouring of balcony topping slabs to falls is nearing completion.
• Ongoing installation of waterproof membrane to balconies.
• The block retaining wall has been completed.

Explore Verge Apartments

Te Awa Terraces

We are absolutely thrilled to share some fantastic news with you – the journey toward your dream home at Te Awa Terraces has officially begun! Over the past two weeks, our civils and infrastructure contractor has been hard at work.

 

The site has undergone a significant transformation with the demolition of existing buildings and clearing of debris and rubbish. With the site now cleared, our contractors are working to implement all sediment and erosion controls before commencing earthworks.

Image 1
Rectangle 3475

Verge Apartments

We are delighted to provide you with the latest updates for Verge Apartments, where every day brings us closer to the realisation of your future home. Our dedicated team of over 200 people have been hard at work on-site and we are excited to share the latest developments across the East and West Buildings.

From structural milestones including the installation of the roof to significant interior preparations, your investment is steadily taking shape. Read on to explore the specific achievements and progress across both buildings.

East Building

• External Wall Steel framing in the east building has been installed across levels 1, 2 & 3 and progressing.
• Floor set outs and floor cuts have been marked up across both buildings.
• Interior wall set out is progressing.
• Interior drainage distribution has commenced.

Image 1
Rectangle 3475
Image 1

West Building

• Roof guttering has been completed.
• External wall steel framing in the West building has been installed across levels 2 & 3 and progressing.
• Floor set outs and floor cuts have been marked up across both buildings.
• Interior wall set out is progressing.
• Interior drainage distribution has commenced.

Mountain Vista Estate

It brings us great pleasure to provide you with the latest updates on the development progress at Mountain Vista Estate. As our dedicated team tirelessly works towards making your dream homes a reality, we’re excited to share the latest achievements and milestones across all stages of the project.

From the meticulous insulation to the timely structural advancements and upcoming painting schedules, your investment is flourishing. Read on to explore the specifics of your respective blocks and Stage 3 in our comprehensive development update.

Image 1

Block 1

• Wall insulation complete.
• Intello installation complete.
• Stair installation complete.
• Gib works complete.
• Gib stops substantially complete.
• Painting due to commence during September.

 

Block 2

• Remediation has now been finalised.
• New PLTs delivered.
• Structural works progressing.

Block 3

• 1st fix works complete.
• Stair installation complete.
• Insulation complete.
• Intello complete.
• Gib to walls complete.

 

Block 4
• Remediation has been finalised.
• New PLTs delivered.
• Structural works progressing.
• Roof finishes forecasted for September.

 

Block 5

• Gib delivered.
• 1st fix works completed.
• Stair installation complete.
• Gib installation complete.
• Gib stopping ongoing.
• Painting due to commence during September.

 

Block 6

• New PLTs delivered.
• Structural works are progressing nicely.
• Roof finishes forecast for September.

 

Block 7

• Roofing and flashes complete.
• Building weathertight.
• Gib has been procured.
• 1st fix works completed.
• Gib installation forecast to commence beginning of September.

 

Block 8

• Roofing and flashings complete.
• Building dry out completed.
• Stair installation complete.
• Windows installed.
• 1st fix works forecast to commence September.
• Gib installation forecast to commence September.

Rectangle 3475

Block 9

• Roofing and flashings complete.
• 1st fix services complete.
• Building weathertight – Windows installed.
• Gib procured.
• Insulation due to commence September.
• Intello install due to commence September.

 

Block 10

• Roofing and flashings complete.
• Windows have been delivered.
• 1st fix services are nearly complete.
• Stairs installed.

 

Block 11

• Roofing and flashings complete.
• Windows have been delivered.
• Insulation forecast to commence September.

Block 12

• Structural works progressing.
• Roof finishes forecast to commence during September.
• Window delivery forecast for September.
• Stairs have now been ordered.

 

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.

DUVAL to invest $105 million in developments across South and West Auckland

DUVAL, one of New Zealand’s largest urban residential property development companies has announced a $105m investment in two new housing projects in South and West Auckland.

Institutional funding has been secured for both projects taking the group’s total facilities to approximately $350 million across its development portfolio.

The company specialises in regenerating brownfield sites and building master-planned communities and the two projects Te Awa Terraces situated at Earlsworth Road, Māngere East and Sunnyvale Terraces on Awaroa Road, Sunnyvale will provide 125 new homes. Completion is anticipated to be Q3 in and Q4 2024.

DUVAL is committed to providing quality affordable and aspirational housing in the Auckland region and now has 403 homes under construction with further plans to commence work on an additional 100 homes this year.

DVP_Aug23_NZHImage_5

Charlotte Clarke, Chief Executive of the DUVAL Property Group said, “I am delighted that we are starting construction on these two new projects. The outlook for the housing sector is strong over the medium term, with record migration numbers to the Auckland region and clear and present demand for housing. Auckland has the capacity for over 900,000 infill housing units within its urban-zoned land and over time this will reduce the burden on the city’s infrastructure. We anticipate housing intensification while preserving the green belt is going to be critical for the growth of New Zealand’s largest city.”

“We have to go up, not out if ratepayers aren’t going to bear the burden of unchecked urban sprawl,” Clarke went on to say.

Kristen Holland, the General Manager of Development at DUVAL, emphasised, “We are firm believers in our corporate responsibility to enhance the living conditions of our communities by repurposing land and increasing the supply of new housing.”

These investments mark the ninth master-planned community developed by DUVAL within the south of Auckland and the second within Auckland’s west.

Te Awa Terraces is in close proximity to DUVAL’s $150 million Mountain Vista Estate project where work has started on Stage 3.

Holland said, “Enquiry for new housing this year remained steady, highlighting the resilience of the sector. Stages 1 and 2 are completely sold out and Stage 3 will be released to the market in Q4 2023.”

DVP_Aug23_NZHImage_4

Te Awa Terraces – Earlsworth Road, Māngere East

Te Awa Terraces will become a vibrant new community featuring 79 modern terraces situated in Māngere East, in close proximity to Middlemore Hospital, Auckland International Airport and within Auckland’s commuter belt. These architecturally designed townhouses present spacious two-bedroom layouts, one bathroom and guest toilet, and dedicated parking all set within a master-planned community.

Over the past decade, Māngere East has had an average capital growth rate of 10% p.a.*

For more information about Te Awa Terraces, visit

Sunnyvale Terraces – Awaroa Road, Sunnyvale

Sunnyvale Terraces will comprise 46 homes in the heart of Sunnyvale, in Auckland’s west. A peaceful suburban development and community located a short distance from West City shopping mall, Costco and walking distance to the Sunnyvale train station providing a direct link to the CBD, Newmarket and Eden Park.

Spanning two levels, these immaculately presented townhouses feature two bedrooms, large open-plan living areas, spacious bathrooms, a guest toilet, and dedicated car parking.

Over the past decade, Sunnyvale has had an average capital growth rate of 7.9% p.a.*

For more information about Sunnyvale Terraces visit

*CoreLogic (August 2023)

Mountain Vista Estate

We’re thrilled to provide you with a comprehensive progress update on your home at Mountain Vista Estate. Each block has seen remarkable strides, and we’re eager to share these exciting developments with you. From completed roofing and weathertight building structures to the initiation of exterior work and the ordering of essential components like stairs and Gib, your dream home is taking shape in inspiring ways. Let’s delve into the details of each block’s accomplishments and set the stage for the journey that lies ahead.

DVCO_Apr23_VergePUPhotos_1

Block 1

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services substantially complete.
• Gib ordered.
• Stairs ordered.

Block 2

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 3

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope complete.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 4

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

DVCO_Apr23_VergePUPhotos_1

Block 5

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 6

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 7

• Roof trusses completed reconstruction and amended.
• Roof sheeting on site pending installation.
• Stairs ordered.

Block 8

• All roofing completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 9

• Roof finishes complete.
• Window delivery expected in August.
• Stairs ordered.

Block 10

• Roofing works commenced.
• Stairs ordered.

Block 11

• Structure remediation completed.
• Roof framing completed.
• Roof measure completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 12
• Structure in progress to first floor.
• Stairs ordered.

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.

MVE_3

Verge Apartments

We’re thrilled to update you on the progress of the East and West Buildings of Verge apartments. In the East Building, mechanical equipment installation on levels 1-3 is complete, along with external wall steel framing. Roofing work is advancing on level 4, and basement electrical services are in place.

In the West Building, roof purlins are installed, steel framing has begun, and mechanical equipment is on levels 1-3. Scaffold is up on the West and South elevations, and transformer installation is finished. We are making some really impressive headway!

DVCO_Apr23_VergePUPhotos_1

East Building

Install RAB weather-line and proclima paper.
Install additional steelwork to lift shaft.
Install sprinkler system and hydrants.

West Building

Complete penetrations to steel frame on all floors.
Install sprinkler system and hydrants.
Pour topping slabs to falls for all balconies

DVCO_Apr23_VergePUPhotos_1

Mountain Vista Estate

Stage 1

• Block 1 - Superstructure and Roofing installation is complete – Window install scheduled to start next week followed by the cavity system.
• Block 3 - Internal gutter framing and waterproofing (at roof level) completed – Roof installation next week, followed by the cavity system.
• Block 5 - Roof framing complete – Roof installation next week, followed by the cavity system.
• Block 7 - Roof/internal gutter framing and waterproofing completed – Roof installation scheduled to begin in 2 weeks.

Stage 2

• Block 8 - Superstructure completed, building wrapped – Roof install to begin in 3 weeks.
• Block 9 - Internal gutters completed – waterproofing and roof to being in 2-3 weeks.
• Block 10 - Roof framing completed, ready to roof.
• Block 11 - Roof framing completed, gutters and waterproofing to begin next week.
• Block 12 - Subfloor bearers have been installed – Ground floor PLT installation (Foundation) to begin in 1-2 weeks.

DVCO_Apr23_VergePUPhotos_1

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 of MVE until the completion of Stages 1 and 2.