Parry Terraces

Our construction team are rapidly progressing with the first round of electrical cabling and plumbing installation. The GIB board has arrived on site, and will be installed as soon as the roofing is complete. This will provide your home with extra protection from the wind and an additional acoustic barrier.

All civil works are nearly finished and soon there will be full public access to the site with the last footpaths and vehicle crossings being poured.

2022-06-23 Project Updates-Mountain Vista Estate-17-57

The superstructure for the site is 80% complete with blocks 3 and 4 frames now installed and ready for the roof PLTs to be fitted. The superstructure consists of everything above baseline such as the framing, floors and roof. All road signage including street names has been ordered and we cannot wait to officially mark Parry Terraces within Mount Wellington.