Mountain Vista Estate

It brings us great pleasure to provide you with the latest updates on the development progress at Mountain Vista Estate. As our dedicated team tirelessly works towards making your dream homes a reality, we’re excited to share the latest achievements and milestones across all stages of the project.

From the meticulous insulation to the timely structural advancements and upcoming painting schedules, your investment is flourishing. Read on to explore the specifics of your respective blocks and Stage 3 in our comprehensive development update.

Image 1

Block 1

• Wall insulation complete.
• Intello installation complete.
• Stair installation complete.
• Gib works complete.
• Gib stops substantially complete.
• Painting due to commence during September.

 

Block 2

• Remediation has now been finalised.
• New PLTs delivered.
• Structural works progressing.

Block 3

• 1st fix works complete.
• Stair installation complete.
• Insulation complete.
• Intello complete.
• Gib to walls complete.

 

Block 4
• Remediation has been finalised.
• New PLTs delivered.
• Structural works progressing.
• Roof finishes forecasted for September.

 

Block 5

• Gib delivered.
• 1st fix works completed.
• Stair installation complete.
• Gib installation complete.
• Gib stopping ongoing.
• Painting due to commence during September.

 

Block 6

• New PLTs delivered.
• Structural works are progressing nicely.
• Roof finishes forecast for September.

 

Block 7

• Roofing and flashes complete.
• Building weathertight.
• Gib has been procured.
• 1st fix works completed.
• Gib installation forecast to commence beginning of September.

 

Block 8

• Roofing and flashings complete.
• Building dry out completed.
• Stair installation complete.
• Windows installed.
• 1st fix works forecast to commence September.
• Gib installation forecast to commence September.

Rectangle 3475

Block 9

• Roofing and flashings complete.
• 1st fix services complete.
• Building weathertight – Windows installed.
• Gib procured.
• Insulation due to commence September.
• Intello install due to commence September.

 

Block 10

• Roofing and flashings complete.
• Windows have been delivered.
• 1st fix services are nearly complete.
• Stairs installed.

 

Block 11

• Roofing and flashings complete.
• Windows have been delivered.
• Insulation forecast to commence September.

Block 12

• Structural works progressing.
• Roof finishes forecast to commence during September.
• Window delivery forecast for September.
• Stairs have now been ordered.

 

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.