Mountain Vista Estate

We’re thrilled to provide you with a comprehensive progress update on your home at Mountain Vista Estate. Each block has seen remarkable strides, and we’re eager to share these exciting developments with you. From completed roofing and weathertight building structures to the initiation of exterior work and the ordering of essential components like stairs and Gib, your dream home is taking shape in inspiring ways. Let’s delve into the details of each block’s accomplishments and set the stage for the journey that lies ahead.

DVCO_Apr23_VergePUPhotos_1

Block 1

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services substantially complete.
• Gib ordered.
• Stairs ordered.

Block 2

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 3

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope complete.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 4

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

DVCO_Apr23_VergePUPhotos_1

Block 5

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 6

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 7

• Roof trusses completed reconstruction and amended.
• Roof sheeting on site pending installation.
• Stairs ordered.

Block 8

• All roofing completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 9

• Roof finishes complete.
• Window delivery expected in August.
• Stairs ordered.

Block 10

• Roofing works commenced.
• Stairs ordered.

Block 11

• Structure remediation completed.
• Roof framing completed.
• Roof measure completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 12
• Structure in progress to first floor.
• Stairs ordered.

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.

MVE_3