Mountain Vista Estate

Stage 1

• Block 1 - Superstructure and Roofing installation is complete – Window install scheduled to start next week followed by the cavity system.
• Block 3 - Internal gutter framing and waterproofing (at roof level) completed – Roof installation next week, followed by the cavity system.
• Block 5 - Roof framing complete – Roof installation next week, followed by the cavity system.
• Block 7 - Roof/internal gutter framing and waterproofing completed – Roof installation scheduled to begin in 2 weeks.

Stage 2

• Block 8 - Superstructure completed, building wrapped – Roof install to begin in 3 weeks.
• Block 9 - Internal gutters completed – waterproofing and roof to being in 2-3 weeks.
• Block 10 - Roof framing completed, ready to roof.
• Block 11 - Roof framing completed, gutters and waterproofing to begin next week.
• Block 12 - Subfloor bearers have been installed – Ground floor PLT installation (Foundation) to begin in 1-2 weeks.

DVCO_Apr23_VergePUPhotos_1

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 of MVE until the completion of Stages 1 and 2.