Mountain Vista Estate
We are excited to provide our first project update for 2024 regarding Mountain Vista Estate. The year has kicked off well and we’re thrilled to share the progress we’ve made on your property!
We’re pleased to inform you that we’ve obtained Code of Compliance for Stage 1 (blocks 1, 3, 5, and 7) and Stage 2 (blocks 8,9,10,11 and 12), with settlements due very soon pending the issuance of 224C and subsequent titles.
The 224C approval is awaiting the final green light from the Auckland council parks concerning the esplanade reserve, which is expected imminently. We anticipate practical completion for the remaining blocks in Stage 1 in April.
Stage 3 has seen significant advancements, with trades tirelessly working throughout the summer break.
On site, Stage 3 is broken down into a further three stages, known internally as stages 3, 4 and 5. Stage 3 drainage, structural work, joinery, and cladding have all been completed and approved. Additionally, Stage 4 (the apartment block) has received approval for civils, fitout and façade consent, and work is scheduled to commence shortly. Stage 5 consents have also been approved, marking another significant milestone in our progress.
Thank you for your continued trust and support in our project.