Mountain Vista Estate

In this project update, we are excited to share the significant milestones achieved in recent months and to offer a glimpse into the promising future that lies ahead. Our commitment to excellence, the dedication of our team, and your support have all played crucial roles in bringing this vision to life.

Please read on to discover the remarkable progress and the path we’re embarking on as we continue our journey towards creating a truly exceptional living experience at Mountain Vista Estate.

Block 1

• Interior painting is complete.
• Timber flooring is complete.
• Waterproofing and tiles are 95% complete.
• Finishing lines are complete in Units 1 & 2, and      90% complete in Units 3, 4 & 5.
• Second fix plumbing is 30% complete.
• Second fix electrical and mechanical is 50% complete.

Block 2

• Membrane gutters are currently at 50% completion.
• RAB / Play installation is currently at 60% completion.
• Exterior building wrap is at 95% completion.

Rectangle 3475

Block 3

• Interior door installation is complete.
• Finishing lines are currently substantially complete across all units.
• Plaster is substantially complete across all units.
• Waterproofing and tiles are substantially complete.

 

Block 4
• Roof installation has been completed.
• Windows are currently not on site for installation.
• RAB / Ply installation is at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 5

• Finishing lines are 80% complete across each unit.
• Paint is substantially complete.
• Waterproofing and tiles are substantially complete across all units.
• Kitchen joinery is being installed within 5 of the 8 units. Currently 80% complete across these units.
• 2nd plumbing fix is 30% complete across all units.

Block 6

• Roof installation has been completed.
• Window installation is at 75% completion and progressing.
• RAB / Ply is currently at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 7

• Roofing and flashings complete.
• Waterproofing and tiles are substantially complete across all units.
• Paint sealer coat has been completed across all units.
• Paint topcoat is currently 70% complete across all units.

 

Block 8

• First fix has been completed across all units.
• Insulation and Intello have been completed across all units.
• Battens have been installed across all units.
• Gib work has commenced on 2nd October.

Rectangle 3475

Block 9

• Gib installation has been completed.
• Finishing lines are 70% complete across all units.
• Plastering is progressing at 50% throughout the remaining units.
• Internal doors are currently being installed.

 

Block 10

• 1st fix has been completed across all units.
• Gib installation on walls has been completed across all units.
• Ceiling gib is currently progressing.

 

Block 11

• 1st fix has been completed across all units.
• Insulation and Intello has been completed across all units.
• Battens have been installed across all units.
• Gib installation is currently progressing across all units.

Block 12

• Stairs have been installed across all units.
• 1st fix has been completed across all units.
• Insulation and Intello has been installed across all units.
• Structures are all complete.
• All roof installation and finishes have been completed.
• All windows have been installed.
• Battens have been installed across all units.
• Gib installation on walls is currently progressing.

 

Block 13

• Basement beams have been installed.
• Basements slabs have been installed.
• Installation of Novacoil & Scoria is currently 75% complete with backfill.