Te Awa Terraces

We are pleased to provide you with the latest update on the progress of the Te Awa Terraces project for the first quarter of 2024.

  • All earthworks have been successfully completed, marking a significant milestone in the project’s development.
  • Kerb and channel work for the roadway have been finished, enhancing the infrastructure of the development.
  • Concrete pouring for the road will commence shortly, with carparks already benefiting from laid concrete.
  • Under-slab services are currently underway, and preparations for laying concrete slabs have begun, demonstrating steady progress in the construction phase.
Teawaimage_2
  • We are excited to announce that 45% of the properties in the development have already been sold, indicating strong market interest and demand.Our program is currently tracking on times which indicates that settlements are projected for Q4 of this year, outlining our commitment to delivering your a home within the outlined timeline.
  • The project is estimated to be completed by the end of the year 2024, with settlement aimed for the end of 2024 or early 2025.
  • We are committed to closely monitoring progress and will provide a more precise timeline update in our upcoming communications to ensure transparency and clarity for all stakeholders.