Mountain Vista Estate

Stages 1 & 2

  • Stages 1 & 2 are on schedule for completion by early December 2023, with the title expected shortly thereafter. Settlement is anticipated in December 2023 / January 2024, and regular updates will be provided.
  • Block 1 has successfully completed all construction phases, including final inspections and council approval.

 

  • Blocks 2, 4, and 6 are progressing as planned, with settlements anticipated in January / February 2024.
    The road connecting stages 2 & 3 has been finished, enhancing accessibility and connectivity within the project.
Rectangle 3475

Stage 3

  • Stage 3 is actively under construction, with substantial progress noted.
  • Concrete pouring is underway for the ground floor of the apartment and commercial block, while the first-floor framing is already in place.

 

  • Blocks 16 & 18 framing has been completed, and we anticipate the framing for 15 & 17 before Christmas.
  • Site offices and storage containers along the road front are being relocated or removed to facilitate the preparation of concrete pads for blocks 19 - 22.
Rectangle 3475

Explore Mountain Vista Estate

Mountain Vista Estate

In this project update, we are excited to share the significant milestones achieved in recent months and to offer a glimpse into the promising future that lies ahead. Our commitment to excellence, the dedication of our team, and your support have all played crucial roles in bringing this vision to life.

Please read on to discover the remarkable progress and the path we’re embarking on as we continue our journey towards creating a truly exceptional living experience at Mountain Vista Estate.

Block 1

• Interior painting is complete.
• Timber flooring is complete.
• Waterproofing and tiles are 95% complete.
• Finishing lines are complete in Units 1 & 2, and      90% complete in Units 3, 4 & 5.
• Second fix plumbing is 30% complete.
• Second fix electrical and mechanical is 50% complete.

Block 2

• Membrane gutters are currently at 50% completion.
• RAB / Play installation is currently at 60% completion.
• Exterior building wrap is at 95% completion.

Rectangle 3475

Block 3

• Interior door installation is complete.
• Finishing lines are currently substantially complete across all units.
• Plaster is substantially complete across all units.
• Waterproofing and tiles are substantially complete.

 

Block 4
• Roof installation has been completed.
• Windows are currently not on site for installation.
• RAB / Ply installation is at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 5

• Finishing lines are 80% complete across each unit.
• Paint is substantially complete.
• Waterproofing and tiles are substantially complete across all units.
• Kitchen joinery is being installed within 5 of the 8 units. Currently 80% complete across these units.
• 2nd plumbing fix is 30% complete across all units.

Block 6

• Roof installation has been completed.
• Window installation is at 75% completion and progressing.
• RAB / Ply is currently at 95% completion.
• Exterior building wrap is at 95% completion.

 

Block 7

• Roofing and flashings complete.
• Waterproofing and tiles are substantially complete across all units.
• Paint sealer coat has been completed across all units.
• Paint topcoat is currently 70% complete across all units.

 

Block 8

• First fix has been completed across all units.
• Insulation and Intello have been completed across all units.
• Battens have been installed across all units.
• Gib work has commenced on 2nd October.

Rectangle 3475

Block 9

• Gib installation has been completed.
• Finishing lines are 70% complete across all units.
• Plastering is progressing at 50% throughout the remaining units.
• Internal doors are currently being installed.

 

Block 10

• 1st fix has been completed across all units.
• Gib installation on walls has been completed across all units.
• Ceiling gib is currently progressing.

 

Block 11

• 1st fix has been completed across all units.
• Insulation and Intello has been completed across all units.
• Battens have been installed across all units.
• Gib installation is currently progressing across all units.

Block 12

• Stairs have been installed across all units.
• 1st fix has been completed across all units.
• Insulation and Intello has been installed across all units.
• Structures are all complete.
• All roof installation and finishes have been completed.
• All windows have been installed.
• Battens have been installed across all units.
• Gib installation on walls is currently progressing.

 

Block 13

• Basement beams have been installed.
• Basements slabs have been installed.
• Installation of Novacoil & Scoria is currently 75% complete with backfill.

Explore Mountain Vista Estate

Verge Apartments

It brings us great pleasure to provide you with the latest updates on our Verge Apartments project. Our team has been diligently working to bring this vision to life, and we are excited to share the significant progress we’ve made.

From the successful installation of the plumbing system to the ongoing pre-wiring and advanced weather line installations, we have reached important milestones. The internal studs are now in place, and the roofing is fully installed.

Rectangle 3475

East Building

• Construction of block wall in the West Building elevation has been completed.
• Roof diamondtek sheeting installation has been completed.
• Internal steel framing on level 2 of the East Building has been completed.
• Penetrations through ComFlor in the East Building have been completed.

• Installation of additional steelwork to the lift shaft has been completed.
• The installation of RAB weather-line and proclima paper is now ongoing with installation progressing from the top-down.
• The completion of external intumescent paint to all floors is ongoing.
• The pouring of topping slabs to falls for all balconies is nearing completion.

Rectangle 3475
Image 2

West Building

• Installation of internal steel framing is ongoing with the demark of all apartments underway.
• Ongoing installation of Airmaster mechanical equipment on Level 4.
• The installation of the roof structure on Level 4 has been completed.
• The pouring of balcony topping slabs to falls is nearing completion.
• Ongoing installation of waterproof membrane to balconies.
• The block retaining wall has been completed.

Explore Verge Apartments

Te Awa Terraces

We are absolutely thrilled to share some fantastic news with you – the journey toward your dream home at Te Awa Terraces has officially begun! Over the past two weeks, our civils and infrastructure contractor has been hard at work.

 

The site has undergone a significant transformation with the demolition of existing buildings and clearing of debris and rubbish. With the site now cleared, our contractors are working to implement all sediment and erosion controls before commencing earthworks.

Image 1
Rectangle 3475

Verge Apartments

We are delighted to provide you with the latest updates for Verge Apartments, where every day brings us closer to the realisation of your future home. Our dedicated team of over 200 people have been hard at work on-site and we are excited to share the latest developments across the East and West Buildings.

From structural milestones including the installation of the roof to significant interior preparations, your investment is steadily taking shape. Read on to explore the specific achievements and progress across both buildings.

East Building

• External Wall Steel framing in the east building has been installed across levels 1, 2 & 3 and progressing.
• Floor set outs and floor cuts have been marked up across both buildings.
• Interior wall set out is progressing.
• Interior drainage distribution has commenced.

Image 1
Rectangle 3475
Image 1

West Building

• Roof guttering has been completed.
• External wall steel framing in the West building has been installed across levels 2 & 3 and progressing.
• Floor set outs and floor cuts have been marked up across both buildings.
• Interior wall set out is progressing.
• Interior drainage distribution has commenced.

Mountain Vista Estate

It brings us great pleasure to provide you with the latest updates on the development progress at Mountain Vista Estate. As our dedicated team tirelessly works towards making your dream homes a reality, we’re excited to share the latest achievements and milestones across all stages of the project.

From the meticulous insulation to the timely structural advancements and upcoming painting schedules, your investment is flourishing. Read on to explore the specifics of your respective blocks and Stage 3 in our comprehensive development update.

Image 1

Block 1

• Wall insulation complete.
• Intello installation complete.
• Stair installation complete.
• Gib works complete.
• Gib stops substantially complete.
• Painting due to commence during September.

 

Block 2

• Remediation has now been finalised.
• New PLTs delivered.
• Structural works progressing.

Block 3

• 1st fix works complete.
• Stair installation complete.
• Insulation complete.
• Intello complete.
• Gib to walls complete.

 

Block 4
• Remediation has been finalised.
• New PLTs delivered.
• Structural works progressing.
• Roof finishes forecasted for September.

 

Block 5

• Gib delivered.
• 1st fix works completed.
• Stair installation complete.
• Gib installation complete.
• Gib stopping ongoing.
• Painting due to commence during September.

 

Block 6

• New PLTs delivered.
• Structural works are progressing nicely.
• Roof finishes forecast for September.

 

Block 7

• Roofing and flashes complete.
• Building weathertight.
• Gib has been procured.
• 1st fix works completed.
• Gib installation forecast to commence beginning of September.

 

Block 8

• Roofing and flashings complete.
• Building dry out completed.
• Stair installation complete.
• Windows installed.
• 1st fix works forecast to commence September.
• Gib installation forecast to commence September.

Rectangle 3475

Block 9

• Roofing and flashings complete.
• 1st fix services complete.
• Building weathertight – Windows installed.
• Gib procured.
• Insulation due to commence September.
• Intello install due to commence September.

 

Block 10

• Roofing and flashings complete.
• Windows have been delivered.
• 1st fix services are nearly complete.
• Stairs installed.

 

Block 11

• Roofing and flashings complete.
• Windows have been delivered.
• Insulation forecast to commence September.

Block 12

• Structural works progressing.
• Roof finishes forecast to commence during September.
• Window delivery forecast for September.
• Stairs have now been ordered.

 

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.

Mountain Vista Estate

We’re thrilled to provide you with a comprehensive progress update on your home at Mountain Vista Estate. Each block has seen remarkable strides, and we’re eager to share these exciting developments with you. From completed roofing and weathertight building structures to the initiation of exterior work and the ordering of essential components like stairs and Gib, your dream home is taking shape in inspiring ways. Let’s delve into the details of each block’s accomplishments and set the stage for the journey that lies ahead.

DVCO_Apr23_VergePUPhotos_1

Block 1

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services substantially complete.
• Gib ordered.
• Stairs ordered.

Block 2

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 3

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope complete.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 4

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

DVCO_Apr23_VergePUPhotos_1

Block 5

• Roofing and flashings complete.
• Window installation complete.
• Building weathertight.
• Exterior envelope commenced.
• 1st fix services testing of previous install substantially complete.
• Gib ordered.
• Stairs ordered.

Block 6

• Deconstruction of framing and PLT’s completed to ground floor.
• New PLT’s to be delivered in August.
• Framing remediation to commence prior to PLT delivery.

Block 7

• Roof trusses completed reconstruction and amended.
• Roof sheeting on site pending installation.
• Stairs ordered.

Block 8

• All roofing completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 9

• Roof finishes complete.
• Window delivery expected in August.
• Stairs ordered.

Block 10

• Roofing works commenced.
• Stairs ordered.

Block 11

• Structure remediation completed.
• Roof framing completed.
• Roof measure completed.
• Roof finishes forecast completion in August.
• Stairs ordered.

Block 12
• Structure in progress to first floor.
• Stairs ordered.

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 until the completion of Stages 1 and 2.

MVE_3

Verge Apartments

We’re thrilled to update you on the progress of the East and West Buildings of Verge apartments. In the East Building, mechanical equipment installation on levels 1-3 is complete, along with external wall steel framing. Roofing work is advancing on level 4, and basement electrical services are in place.

In the West Building, roof purlins are installed, steel framing has begun, and mechanical equipment is on levels 1-3. Scaffold is up on the West and South elevations, and transformer installation is finished. We are making some really impressive headway!

DVCO_Apr23_VergePUPhotos_1

East Building

Install RAB weather-line and proclima paper.
Install additional steelwork to lift shaft.
Install sprinkler system and hydrants.

West Building

Complete penetrations to steel frame on all floors.
Install sprinkler system and hydrants.
Pour topping slabs to falls for all balconies

DVCO_Apr23_VergePUPhotos_1

Mountain Vista Estate

Stage 1

• Block 1 - Superstructure and Roofing installation is complete – Window install scheduled to start next week followed by the cavity system.
• Block 3 - Internal gutter framing and waterproofing (at roof level) completed – Roof installation next week, followed by the cavity system.
• Block 5 - Roof framing complete – Roof installation next week, followed by the cavity system.
• Block 7 - Roof/internal gutter framing and waterproofing completed – Roof installation scheduled to begin in 2 weeks.

Stage 2

• Block 8 - Superstructure completed, building wrapped – Roof install to begin in 3 weeks.
• Block 9 - Internal gutters completed – waterproofing and roof to being in 2-3 weeks.
• Block 10 - Roof framing completed, ready to roof.
• Block 11 - Roof framing completed, gutters and waterproofing to begin next week.
• Block 12 - Subfloor bearers have been installed – Ground floor PLT installation (Foundation) to begin in 1-2 weeks.

DVCO_Apr23_VergePUPhotos_1

Stage 3

• As per previous correspondence, we are expecting to see only small amounts of progress on Stage 3 of MVE until the completion of Stages 1 and 2.

Parry Terraces

During this month, significant progress has been made across multiple blocks of Parry Terraces. In Block 1, the external fencing posts are in place, and retaining walls are ready for the final touches on the patios. Additionally, downpipes have been connected, and brickwork is completed. Internally, door hardware installation and the remaining tiling work have been successfully finished.

In Block 2, the external fence posts and rails are in position, and the click-to-brick work is completed. Inside the units, high wall units have been installed, and most of the carpet installation is finished. Kitchen units are also completed, and HWC strapping has been installed. Similar progress can be seen in Blocks 3, 4, and 5, with various external and internal tasks nearing completion, such as brickwork, decking, driveway preparation, and garage door installations.

Block 1

• Externally fencing posts are in and retaining walls ready for patios to be finished off. Downpipes are connected. Brick works complete (click to brick), ORG’s completed.
• Block 1 internally door hardware completed remaining tiling completed, patching/defects completed.

Block 2

• Externally fence posts have been placed and rails. Click to brick completed brick works.
• Internally high wall units have been installed, passive fire completed, remainder of carpet install completed, kitchen units completed. HWC installed strapping.

Block 3

• Externally cut out and fill of GAP 65 outdoor living areas installed, Brick works completed (click to brick). All timber decks have been installed apart from balustrade. Install of strip drain completed and base prep completed and ready for concrete pour to driveways and foot paths leading into the units.
• Internally passive fire remedial completed, high wall units install complete, mid floor timber flooring completed, floor prep for carpets completed, kitchen units finished tomorrow throughout. Garage doors installed.

DVCO_Apr23_VergePUPhotos_1

Block 4

• Externally footpaths and driveway prepped and formwork in place, ready for concrete pour. Down pipes installed. Cut and export excess materials for patio areas completed. Click to brick completed brick works apart from 1 wing-wall.
• Internals painting throughout all units completed, all units have ceramic tiles apart from 2 units, garage doors installed, unit 17 has been installed with kitchen. Second fix throughout all units have been completed apart from the kitchen cabinetry (electrical).

Block 5

• Externally installed 95% of the balconies and wing-walls, painting externally completed.
• Internally painting finished, garage doors completed, excavating driveways and footpaths into entry underway.

NOTE

• All street lighting and bollards have been installed throughout the complex.

DVCO_Apr23_VergePUPhotos_1